Cementation

DesignBuild

Aug 2, 2013

Goldcorp - Porcupine Gold Mines – Hoyle Deep #2 Winze Project

Cementation was originally awarded and carried out the design engineering work for the Hoyle Deep #2 Winze Project by Goldcorp Canada. Under a separate scope of work Cementation was awarded the shaft sinking and headworks development which in effect changed the project from a traditional shaft sinking contract into a design-build project. This established continuity from design work to construction and one point accountability, all of which were beneficial to the overall construction schedule.

 

Internal shaft sinking projects are known as some of the most technically and logistically challenging projects and it is no coincidence that Cementation is recognized for its experience and expertise in executing winze shaft sinking.

 

 

Goldcorp Inc. -  Red Lake Gold Mines Project

The Red Lake Gold Mines, located in Northwestern Ontario, is owned and operated by Goldcorp Inc. The mine is comprised of the Red Lake Complex and the Campbell Complex.

 

In 2003, Cementation secured the contract to design and sink the No. 3 Shaft, and design the associated surface plant infrastructure. Merging engineering and construction capabilities, the work was carried out as a design-build project. The No. 3 Shaft, a key element in the mine's expansion, was sunk 2179 m from surface with a diameter of 6.55 m. Upon completion of the shaft, Cementation was retained to operate the shaft facilities.

 

Concurrent with the sinking project, Cementation was awarded and started the raise boring of the ventilation circuit for the new No. 3 Shaft in 2005. This project included the drilling of two raises at a diameter of 4 m and two raises at a diameter of 5.52 m for a total of 1945 m. The two raises with diameters of 5.52 m were completed in-line for a total length of 1010 m. This project set a record for the longest, largest diameter single pass raise bored in the Canadian Shield at 694 m long, 5.52m in diameter and completed without any injuries.

 

 

Hecla Mining Company - Lucky Friday #4 Shaft Project

Cementation is carrying out the design and development of the #4 shaft winze at the Lucky Friday Mine for Hecla Mining. Initially Cementation worked with the Hecla group in the prefeasibility costing and scheduling along with preliminary design work for their proposed internal shaft. Work on Hecla's historic Lucky Friday Mine located just outside of Coeur d'Alene in Northern Idaho began in November 2009. The scope includes the design and sinking of an 18 ft diameter shaft to a depth of 8800 ft below surface. This is an internal shaft, the top of which is at the 4900 ft depth level of the existing underground mine. Other associated tasks include lateral development, excavation and construction of an underground hoist station and 16 ft diameter ore bins that are 70 ft high, and installations of the hoisting plant and sinking equipment underground.

Additional scope commenced in 2012 and includes the refurbishing of the existing Silver Shaft to surface.


Source: http://cementation.ca/site/projects.php

Shift Boss
  • Carry out all directives of management
  • Read and sign all log books daily
  • Ensure all employees have the knowledge to work safely and efficiently by giving all employees job specific instructions on a daily basis and monitor progress
Shaft Miners
  • Concrete Installation
  • Steel Installation
  • Drilling and Blasting
Raise Miner
  • Bolt, screen and install manways
  • Install platform
  • Provide ground support
Project Technician/Construction Surveyor
  • Construction layouts for anchor bolt locations, grid lines, formwork, concrete piers, and footings in an underground environment
  • Surveying and checking for column plumbness with a total station during structural steel erection in an underground environment
  • Layout hanger locations
Field Positions - Hope Bay Project

Cementation is currently engaged in the grouting program as well as long hole drilling and development of ore headings at the Hope Bay Project, which is located in the Kitikmeot region of Nunavut.

Millwright

In coordination with other crew members the Millwright is responsible for performing mechanical repairs and routine planned maintenance on a variety of fixed plan installations.

Lead Electrician

The Lead Electrician will be expected to work on the tools to complete the installation and commissioning of conveyor belts, including the services and utilities required for the conveyors, including, but not limited to services (power, fire suppression, controls, etc) required for the conveyors.

Hoist Operator

In coordination with other crew members the Hoist Operator follows job procedures and regulations to perform the assigned tasks. 

Heavy Duty Equipment Mechanical Leader

The Heavy Duty Equipment Mechanical Leader is expected to perform preventative maintenance and repairs as required to surface and underground, mobile and stationary equipment.

Heavy Duty Equipment Mechanic

The Heavy Duty Equipment Mechanic is expected to perform preventative maintenance and repairs as required to surface and underground, mobile and stationary equipment.