Home > Supplier Companies > Northec Construction Inc. > Articles > Bloom Lake - Overburden...
Northec Construction Inc.

Bloom Lake - Overburden Stripping

Dec 22, 2015




Type
Mining

Description
Overburden stripping for further development of iron deposit at Bloom Lake mine. Removing 1 million m3  overburden and set aside on dumps in anticipation in order of the mine closure plan and future reforestation.

EBC provided:
supervision, construction services, provision of manpower and equipment for full execution of work.

Client
Cliffs Natural Resources

Value
$6,000,000

Year
2011
 
Location
Fermont, Quebec, Canada




Source: http://www.ebcinc.com/en/projects/mining/26/bloom-lake-overburden-stripping/

ESTIMATOR — ALL LOCATIONS

The incumbent will be asked to estimate the costs of each public or private project for which the company has decided to respond to a call for tenders and participate in the coordination of the project.

PROJECT MANAGER, Timmins

The Project Manager is the primary point-person responsible for planning, executing, and delivering corporate projects on time, within budget, and in accordance to specifications.

PROJECT MANAGER, Ottawa

As Project Manager, you will be responsible for the management and completion of construction projects.