Northec Construction Inc.
Bloom Lake - Dikes and Ditches
Type
Mining
Description
Construction of 10 dikes and ditches totalling nearly 15 km of works including 7 km of ditches and a volume of over 10,000,000 m3 of fill. The project also involved 20 km of additional access roads and the construction of 3 pumping stations and pumping lines network.
Client
Cliffs Natural Resources
Value
$126,000,000
Year
2012-2013
Engineer
AMEC
Location
Fermont, Quebec, Canada
Source: http://www.ebcinc.com/en/projects/mining/25/bloom-lake-dikes-and-ditches/
ESTIMATOR — ALL LOCATIONS
The incumbent will be asked to estimate the costs of each public or private project for which the company has decided to respond to a call for tenders and participate in the coordination of the project.
PROJECT MANAGER, Timmins
The Project Manager is the primary point-person responsible for planning, executing, and delivering corporate projects on time, within budget, and in accordance to specifications.
PROJECT MANAGER, Ottawa
As Project Manager, you will be responsible for the management and completion of construction projects.