Glencore

2020 Half-Year production report

Jul 31, 2020
Today, we’ve released our half-year production report. See the animation and H1 highlights below for a summary of the numbers. 
 
Glencore has delivered an overall strong first-half operating performance amid the unprecedented challenges presented by Covid-19, reflecting both the ability and dedication of our teams to adapt to these difficult conditions. As a responsible operator, our top priority has been to protect the health and safety of our people and the communities that host our businesses.
 
Although some of our industrial operations were temporarily suspended in line with national and regional guidance, or where our risk assessment determined a suspension was appropriate, the majority of our assets continued to operate relatively normally. I am particularly pleased to report a strong operational performance at Katanga, with its ramp-up on track to achieve design capacity by the end of the year.
 
Our Marketing business has also risen to the challenge, delivering robust counter-cyclical earnings. A very strong first-half performance allows us to now raise our full year 2020 EBIT expectations to the top end of our $2.2-$3.2 billion guidance range.
 
In the near-term, we remain alert to the continuing challenges that Covid-19 presents. While we expect our operating cash flow to remain solid, we have the proven ability to quickly adapt to changing market conditions.
 
Ivan Glasenberg,
CEO
 
H1 production highlights
 
  • Own sourced copper production of 588,100 tonnes was 74,900 tonnes (11%) lower than H1 2019, mainly reflecting Mutanda being on care and maintenance in the current period, expected lower grades at Antapaccay and the short-term impact of Antamina’s Covid-19 related demobilisation/remobilisation, partly offset by stronger milling throughput at Collahuasi.
  • Own sourced zinc production of 550,100 tonnes was in line with H1 2019, reflecting stronger grades at the Canadian mines and the various temporary Covid-19 related suspensions at Antamina and other South American operations.
  • Own sourced nickel production of 55,200 tonnes was in line with H1 2019, reflecting a strong period of operations at Murrin offsetting the delayed delivery of matte from the Sudbury smelter to the Nikkelverk refinery.
  • Attributable ferrochrome production of 466,000 tonnes was 333,000 tonnes (42%) lower than H1 2019, mainly reflecting the South African Covid-19 national lockdown during March/April. Smelting operations partly resumed on 1 May, with further capacity expected to be restarted towards the end of Q3. 
  • Coal production of 58.1 million tonnes was 10.1 million tonnes (15%) lower than H1 2019, mainly reflecting the Covid-19 related asset suspensions in Colombia. 
  • Entitlement interest production of 2.6 million barrels was 0.4 million barrels (17%) higher than H1 2019, due to new wells drilled in Equatorial Guinea and Cameroon, which helped to offset the Covid-19 related suspension of the Chad assets.
 

Source: https://www.glencore.com/media-and-insights/insights/2020-half-year-production-report

Railway Labourer
Reporting to the Railway Supervisor, the primary duties of this job include but are not limited to clean switches, frogs and crossing; adjusts and inspect switches, install or replace worn or defective ties, rails, anchors, switch points and frogs, lifts and shims track, inspects and tightens splice bars and other track maintenance duties.
Emergency Measures Technician

Reporting to the Emergency Measures & Mining Rescue Coordinator, you will be responsible of protecting the human and material resources of the company.

Manager Pension Administration

The incumbent in this position supports the Director, Retirement Programs in the strategic administration of all retirement plans and savings programs, including all reporting, governance and the robust management of all external partners.