Alamos Gold Announces Construction Decision on High Return La Yaqui Grande Project with After-Tax IRR of 41%

Jul 28, 2020
TORONTO, July 28, 2020 (GLOBE NEWSWIRE) -- Alamos Gold Inc. (TSX:AGI; NYSE:AGI) (“Alamos” or the “Company”) today reported results of the positive internal economic study completed on its fully permitted La Yaqui Grande project located in the Mulatos District in Sonora, Mexico. Given the project’s strong economics and its proximity to the existing Mulatos operation, the Company is proceeding with construction of the project starting in the second half of 2020.   
 
La Yaqui Grande Project Highlights
 
  • Average annual gold production of 123,000 ounces per year starting in the third quarter of 2022. This will replace higher cost production from the main Mulatos pit, keeping combined production at approximately 150,000 ounces per year
  • Mine-site all-in sustaining costs of $578 per ounce, significantly reducing Mulatos District all-in sustaining costs from the mid-point of previous 2020 guidance of $960 per ounce
  • After-tax net present value (“NPV”) of $165 million at a 5% discount rate and an after-tax internal rate of return (“IRR”) of 41%, using a base case gold price assumption of $1,450 per ounce and a MXN/USD foreign exchange rate of 21:1
  • After-tax NPV of $260 million and an after-tax IRR of 58% at a 5% discount rate using a gold price assumption of $1,750 per ounce and a MXN/USD foreign exchange rate of 21:1
  • Mine life of five years, extending production from the Mulatos District to 2027, based on current Mineral Reserves
  • Initial capital of $137 million to be spent over a two year period starting in the second half of 2020. At a $1,750 per ounce gold price, Mulatos is expected to self finance the development of La Yaqui Grande following which the operation is expected to generate strong free cash flow 1
  • “La Yaqui Grande represents our next low-cost, high-return project in the Mulatos District. This follows the success of the La Yaqui Phase I and Cerro Pelon projects which were both developed on budget and ahead of schedule. Given its bigger scale and low-cost profile, La Yaqui Grande is expected to drive strong free cash flow growth from the Mulatos District in 2022 and beyond,” said John A. McCluskey, President and Chief Executive Officer.   
 
Mineral Reserves and Resources
 
The La Yaqui Grande mine plan and economic analysis are based on Mineral Reserves as of December 31, 2019 which total 19.2 million tonnes (“Mt”), grading 1.17 grams per tonne of gold (“g/t Au”) and 15.88 grams per tonne of silver (“g/t Ag”), containing 724,000 ounces of gold and 9.8 million ounces of silver. Additionally, the project hosts Measured and Indicated Mineral Resources which total 1.3 Mt, grading 1.01 g/t Au and 8.0 g/t Ag, containing 43,000 ounces of gold and 340,000 ounces of silver. These Mineral Resources were not included in the mine plan and represent potential upside.  
 
Economic Analysis
 
La Yaqui Grande’s estimated after-tax IRR is 41% and after-tax NPV is $165 million using a 5% discount rate and assuming a gold price of $1,450 per ounce, silver price of $18 per ounce, and MXN/USD foreign exchange rate of 21:1.
 
Assuming a $1,750 per ounce gold price and $18 per ounce silver price, the after-tax IRR increases to 58% and after-tax NPV increases to $260 million using a 5% discount rate. The mine plan, operating parameters, and capital estimates incorporated in the study are based on actual operating experience, and mining contractor agreements that have been established for the life of the project.
 
Permitting and Project Overview
 
La Yaqui Grande is located approximately 7 kilometres (straight line) from the existing Mulatos operation and is adjacent to the past producing La Yaqui Phase I operation. As with La Yaqui Phase I, La Yaqui Grande will be developed with an independent heap leach pad and crushing circuit.
 
La Yaqui Grande is fully permitted for construction having received approval of the environmental impact assessment (“MIA”) in the second quarter of 2019 and the Change of Land Use permit in the third quarter of 2019. The project will be developed over the next 24 months with initial production expected in the second half of 2022.
 
Mining and Processing
 
La Yaqui Grande will be mined using conventional open pit methods. Ore will be mined and stacked at a rate of 10,000 tpd over a five year mine life based on existing Mineral Reserves. Contract mining will be employed and a jaw crusher and cone crushers from the past producing El Chanate mine will be relocated to the La Yaqui Grande project area. Ore will be crushed through a three-stage crushing circuit, agglomerated, stacked, and leached on an independent leach pad. The resulting gold bearing solution will be processed through carbon columns following which the loaded carbon will be transported to the existing Mulatos plant for final processing.
 
The La Yaqui Grande deposit is highly oxidized with expected average recoveries of 85% over the life of the operation. This is based on metallurgical test work which demonstrated recoveries above 85%, and operating experience at La Yaqui Phase I which hosts similar metallurgy and yielded life of mine recoveries of 90%.
 
Operating Costs
 
Total cash costs are expected to average $539 per ounce and mine-site all-in sustaining costs $578 per ounce over the life of the operation. La Yaqui Grande is expected to supply the majority of annual production from the Mulatos District starting in the second half of 2022, driving a significant reduction in total cash costs and mine-site all-in sustaining costs from the mid-point of previous 2020 guidance of $860 and $960 per ounce, respectively.
 
Lower costs reflect La Yaqui Grande’s favourable metallurgy and higher grades which, at 1.17 g/t Au, are 31% higher than the grade of Mineral Reserves in the main Mulatos pit. This also reflects lower unit mining costs of $2.42 per tonne of material with La Yaqui Grande benefitting from lower haulage distances and improved contract mining rates with significantly higher mining rates relative to the current Mulatos operation. 
 
Capital Costs
 
Total initial capital is estimated to be $137 million and expected to be spent over a two year period starting in the second half of 2020. This includes $15 to $20 million to be spent in the second half of 2020 with the remainder to be spent in 2021 and the first half of 2022. Initial capital includes $74 million for pre-stripping activities and the remainder is for project infrastructure including the construction of the heap leach pad, waste rock dump, water treatment plant and an independent camp to house the workforce, as well as the installation of the crushing circuit from El Chanate. The remaining life of mine capital includes $24 million of sustaining capital and $35 million for reclamation activities.
 
About Alamos
 
Alamos is a Canadian-based intermediate gold producer with diversified production from three operating mines in North America. This includes the Young-Davidson and Island Gold mines in northern Ontario, Canada and the Mulatos mine in Sonora State, Mexico. Additionally, the Company has a significant portfolio of development stage projects in Canada, Mexico, Turkey, and the United States. Alamos employs more than 1,700 people and is committed to the highest standards of sustainable development. The Company’s shares are traded on the TSX and NYSE under the symbol “AGI”.
 
FOR FURTHER INFORMATION, PLEASE CONTACT:
 
Scott K. Parsons
Vice President, Investor Relations
(416) 368-9932 x 5439
 

Source: http://www.auricogold.com/news-and-events/default.aspx#news--widget

MILL PLANNER

Reporting to the Mill General Foreman, the Mill Planner is responsible for planning and scheduling mill mechanical maintenance, shut down and project work, collaborating with the Electrical and Mobile Planners, Mill Supervisors, Operators, Millwrights and Process Engineers.

Director, Sustainability

The Director, Sustainability is responsible for supporting and executing Alamos’ company-wide sustainability strategy with a focus on environmental aspects including, regulatory compliance, environmental permitting as well as stakeholder and community engagement.

Geologist (Core Logger)

Reporting to the Sr. Exploration Geologist, the Geologist will focus on carrying out exploration programs related to geological mapping, geochemical sampling programs, geophysical surveys and drilling and to ensure service and/or operating standards are met (internally and/or externally).