Home > News > Gowest Gold advancing final...

Gowest Gold advancing final steps toward processing and production

Sep 16, 2020


Will 2021 be the year for Gowest Gold? The company has released an update on its progress towards bringing the company’s 100% owned Bradshaw Gold Deposit near Timmins into production.  

“We are more confident than ever that we are on the verge of seeing the Bradshaw gold deposit as a new gold mine in the Timmins camp within the coming year," Greg Romain, Gowest President, said. "I am pleased to provide an update on critical milestones, and look forward to providing our loyal shareholders with regular updates in the coming weeks and months.”

Commercial Production Permit

Gowest has received all environmental permits required to bring the mine into commercial production, with the exception of the Mine Production Closure Plan (“the Closure Plan”), which has now been submitted to Ontario’s Ministry of Energy, Northern Development and Mines (“ENDM”) for final review and filing. According to the Ontario Mining Act, the ENDM has 45-days from September 14, 2020, the date of receipt of the plan, for final review and filing.

This represents the final step towards receiving the Commercial Mine Production permit for Bradshaw. Working with its professional environmental partners, Golder Associates and Blue Heron Environmental, the Company has conducted extensive consultations with Indigenous Communities, the City of Timmins, and government officials related to its planned operations and the Closure Plan. Based on the input from these various groups, Gowest recently completed the final revisions to the Closure Plan, which provides details for how the mine will be operated and closed, and how the site will eventually be reclaimed once mining activities are completed.

Site Operations

Gowest is commencing the start-up of the ore-sorter in preparation for sorting the mixed development ore currently stockpiled on surface, which will be trucked to Northern Sun’s Redstone Mill for processing.  The Redstone Mill operators have advised that they are finalizing the necessary upgrades and that the circuit will be ready to receive the Bradshaw material in a few weeks.

As previously reported, approximately 28,000 tonnes of gold-bearing mixed development ore has been collected and stockpiled on-site from the Company’s ongoing Advanced Exploration Bulk Sample program. The Company also plans to mine approximately 15,000 tonnes of stope ore as part of the bulk sample.

The Company also notes that the vent raise permitting is complete, and construction required for production mining is well underway.

Financing Update

As previously reported, the Company still requires additional funding to meet its operational objectives. Gowest is working with interested parties to complete one or more financings, which are needed to take Bradshaw into production. The submission of the Closure Plan and receipt of the Commercial Production Permit are critical milestones for such financings.

About Gowest

Gowest is a Canadian gold exploration and development company focused on the development of its 100% owned Bradshaw Gold Deposit (Bradshaw), on the Frankfield Property, part of the Company’s North Timmins Gold Project (NTGP).  Gowest is exploring additional gold targets on its more than 100‐square‐kilometre NTGP land package and continues to evaluate the area, which is part of the prolific Timmins, Ontario gold camp.  Currently, Bradshaw contains a National Instrument 43‐101 Indicated Resource estimated at 2.1 million tonnes (“t”) grading 6.19 grams per tonne gold (g/t Au) containing 422 thousand ounces (oz) Au and an Inferred Resource of 3.6 million t grading 6.47 g/t Au containing 755 thousand oz Au. Further, based on the Pre‐Feasibility Study produced by Stantec Mining and announced on June 9, 2015, Bradshaw contains Mineral Reserves (Mineral Resources are inclusive of Mineral Reserves) in the probable category, using a 3 g/t Au cut‐off and utilizing a gold price of US$1,200 / oz, totaling 1.8 million t grading 4.82 g/t Au for 277 thousand oz Au.



Tags: Northern Ontario / Operational Updates / Gold / All Articles